Construction Progress Drives ARQA’s Next Growth Phase in 2026

ARQA Development Group continues to make steady progress across its projects, with construction moving forward at both I Business Park in the New Administrative Capital and Annex26 in 6th of October City.

As work advances on current developments, the company is also preparing for a new project launch later in 2026, supporting its continued growth in the Egyptian real estate market.

I Business Park Takes Shape in the New Administrative Capital

Construction at I Business Park has reached several key milestones.

Concrete works for the retail and administrative areas across the project's three towers have been completed, along with the suspended restaurants, one of the development's standout features.

Work is now progressing on the building façades as the project moves closer to its final construction stages.

Annex26 Moves Forward in 6th of October City

Construction at Annex26 continues to move forward, with all site preparation works completed and the project now preparing for the raft foundation stage.

Expanding Across Key Growth Areas

Over the past year, ARQA has expanded its presence in West Cairo through the launch of Ritz in Sheikh Zayed and Annex26 in 6th of October City.

The company continues to grow its portfolio across residential, commercial, and administrative developments, focusing on locations with strong long-term potential.

Looking Ahead

Alongside the progress being made across its current projects, ARQA is preparing to launch a new development in 2026.

 

The upcoming project will mark another step in the company's growth journey as it continues to expand its presence and deliver new opportunities in the Egyptian market.

×